Emergency Maintenance - Vodafone Leased Line Circuits
Scheduled Maintenance Report for Ai Networks Ltd
Completed
Works are now complete with an updated NTE now installed, testing shows all customer services operational.
Posted Aug 24, 2019 - 01:32 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 23, 2019 - 22:00 BST
Scheduled
Ai Networks will be undertaking emergency maintenance on Friday, 23rd of August 2019 between 22:00 and 02:00. The work being carried out will take place at our Telehouse Data Centre and will effect our Vodafone Leased Lines.

An NTE will be replaced with a new firmware release and tested with 3rd line Vodafone engineers to ensure stability remains on this.
Posted Aug 21, 2019 - 14:51 BST
This scheduled maintenance affected: London Network and National MPLS Network.